After Delays, Neela Gumbad Underground Parking Plaza Gets October 30 Deadline

Lahore: Construction of the Neela Gumbad underground parking plaza at the historic Cycle Market area has entered its finishing stage, with authorities setting October 30, 2026 as the new completion deadline after the project missed its earlier target. Dunya reported that the basic structural work has been completed and finishing, landscaping and beautification work is now being carried out.

The latest Housing Department review separately reported that the Neela Gumbad parking plaza was about 75% complete, confirming that substantial work still remained despite the main structural phase reaching an advanced stage.

The underground facility is being developed by TEPA, under the LDA framework. The project carries a reported cost of about Rs2.451 billion and consists of a ground floor with three basement levels. Earlier project details said it was designed to provide parking for roughly 400 cars and 800 motorcycles, while 62 shops are planned in the first basement for traders affected by the redevelopment of the old Cycle Market.

The project is part of a wider effort to reorganise the Neela Gumbad commercial and heritage area, improve parking and traffic management, and restore visibility around historic structures previously surrounded by commercial encroachments.

Leave a Reply

Your email address will not be published. Required fields are marked *

Related News

Punjab Chief Minister Maryam Nawaz Sharif chaired a special meeting to review food prices, wheat cultivation and the supply of essential commodities. The provincial government

....

LWMC has completed special cleanliness arrangements at Gaddafi Stadium ahead of the Pakistan-England match in the ODI tri-nation series. CEO LWMC Sheryar Arif Khan said

....

Deputy Commissioner Lahore Captain (R) Muhammad Ali Ejaz visited UC-194 Lidhar and Bedian Road to review public-service and development projects. Accompanied by senior municipal and

....