Peshawar: The Peshawar Development Authority reported that approximately 35% of construction work on the Hazarkhawani Overpass Project has been completed. In its official site progress update, the authority said construction activities were continuing around the clock under regular supervision. A target of 230 cubic metres of concrete pouring was set for the night shift to help maintain the existing construction schedule. The figure represents a planned pouring target and was not reported as completed at the time of the update. PDA said continuous execution and site monitoring were being maintained to support infrastructure quality. The available official statement did not provide the project’s total approved cost, complete structural dimensions, contractor details, revised completion date or an independently certified progress report.