Lahore: Construction on the Nasir Bagh and Neela Gumbad underground parking plazas has entered an advanced stage, with finishing and technical works now underway at both projects.
According to the latest LDA update supplied for this report, 83% of the Nasir Bagh parking plaza and 80% of the Neela Gumbad parking plaza have been completed. Painting, electrical works and camera installation are now in progress, while LDA Director General Tahir Farooq has directed project teams to accelerate the remaining work.
Recent LDA-issued updates independently support the advanced construction status. On September 19, LDA reported that the grey structure of the Neela Gumbad plaza was complete, with finishing work underway across all three basement levels. On September 20, it reported that the grey structure of both underground levels at Nasir Bagh had reached 100%, with finishing work continuing. ProPakistani
Earlier reporting said both projects had missed previous completion targets, with a new target of October 30, 2026 reported for their completion.